Item Coversheet
Meeting Date:
7/2/2019
Staff Contact:

Rick Trice, P.E.

Director Public Works


 
Agenda Items:

(4)(b)
E-mail:
rtrice@saginawtx.org
  Phone:(817) 230-0449

SUBJECT:

Action Regarding Authorization of an Individual Project Order (IPO) for FM-156 Utility Relocations




BACKGROUND/DISCUSSION:

The Texas Department of Transportation (TxDOT) is currently improving FM-156 from U.S. – 287 to McLeroy Boulevard. City staff and Kimley-Horn and Associates, Inc. (KHA) has been coordinating with TxDOT for several months to determine the scope of work for required utility relocations in the project corridor. City facilities located within TxDOT right-of-way are required to relocate their facilities when in conflict with proposed TxDOT improvements.

 

The city’s budget included $874,000 in the 2018-19 Capital Improvement Plan for the costs of the relocations. The joint coordination effort resulted in a significantly reduced scope of work.

 

The proposed IPO with KHA will provide engineering plans, specifications and contract documents to complete the relocation of three waterline segments that are in conflict. Bidding and general construction oversight is also included.

 

KHA proposes to perform this work for $47,500.

 

The cost breakdown is as follows:

 

Preliminary Design

$27,500

Lump Sum

Final Design

$7,500

Lump Sum

Bidding

$5,000

Lump Sum

Construction Contract Administration

$7,500

Reimburseable

Total

$47,500

 



FINANCIAL IMPACT:

The fiscal impact will be $47,500. Funds are available from (Capital Projects Fund, Account 05-7023-55-00).  



RECOMMENDATION:

Staff recommends that the IPO with Kimley-Horn for FM-156 Utility Relocations be authorized in the amount of $47,500.

ATTACHMENTS:
Description
Budget Information
KHA IPO