Item Coversheet
Meeting Date:
1/21/2020
Staff Contact:

Rick Trice, P.E.

Director of Public Works


 
Agenda Items:

(4)(c)
E-mail:
rtrice@saginawtx.org
  Phone:(817) 230-0449

SUBJECT:

Action Regarding Award of Contract for FM-156 Utility Relocations




BACKGROUND/DISCUSSION:

The Texas Department of Transportation (TxDOT) is currently improving FM-156 from U.S. – 287 to McLeroy Boulevard. City facilities located within TxDOT right-of-way are required to relocate their facilities when in conflict with proposed TxDOT improvements.

 

On July 2, 2019, City Council authorized an Individual Project Order in the amount of $47,500 with Kimley-Horn to prepare engineering plans, specifications and contract documents to complete the relocation of three waterline segments that are in conflict.

 

The project was advertised and on January 8th, the following bids were received:

 

Bidder

Bid Amount

Gomez Brothers Construction, Inc.

$202,980.00

Reytech Services, LLC

$210,000.00

Grod

$214,230.00

FM Utilities, LLC

$223,569.00

Blackroack Construction

$233,535.00

Atkins Bros.

$252,830.00

Barclays Premier Utility Services, LLC

$257,984.00

Macias Specialty Contracting

$324,960.00

W. Brown Enterprises

$341,900.00

Canary Construction

$352,825.00

Fort Worth Civil Contructors, LLC

$392,980.00

 

Kimley-Horn has reviewed the bids and has recommended the contract be awarded to Gomez Brothers Construction, Inc. in the amount of $202,980.00.



FINANCIAL IMPACT:

The fiscal impact will be $202,980.00. Funds are available in the Capital Projects Fund (Capital Projects Fund, Account 05-7023-55-00).  



RECOMMENDATION:

Staff recommends that the construction contract for the FM-156 Utility Relocations be awarded to Gomez Brothers Construction, Inc. in the amount of $202,980.00.

ATTACHMENTS:
Description
Bid Tabulation
KHA Award Recommendation Letter