SUBJECT:

Action regarding Authorization of an Individual Project Order (IPO) with Kimley-Horn & Associates, Inc. (KHA) for Design of the Northwest Booster Pump Station




BACKGROUND/DISCUSSION:

The northwest area of the City of Saginaw is subject to low water pressure. The lack of pressure can be exacerbated by construction of multistoried housing or business structures. In order to correct the problem construction of a booster pump station is recommended to bring pressures to an acceptable level.

 

KHA has prepared an IPO providing design and construction phase services for the booster pump. The pump will be located adjacent to the Park Center Elevated Storage Tank in William Houston Park.

 

The services and costs for the IPO are as follows:    

Task Name

Budgeted Amount

Fee Type

Conceptual Design

$7,500

Lump Sum

Preliminary Design

$15,000

Lump Sum

Final Design

$25,000

Lump Sum

Bidding

$5,000

Lump Sum

Construction Contract Administration

$10,000

Reimbursable

Total

$62,500




FINANCIAL IMPACT:

The Fiscal Impact of this action is $62,500. Funds will come from Water Impact Fees.



RECOMMENDATION:

It is recommended that the City Council authorize the Award the IPO with KHA for the Northwest Booster Pump Station in the amount of $62,500.